Soft Landings – it’s not all about the cake!

A guest post by Stuart Thompson of Morgan Sindall

Soft Landings Workshop

Soft Landings Workshop

Following on from my previous post regarding the UEA low carbon project I’d like to share our progress with the inclusion of Soft Landings.

Last week our soft landings champions met for our fifth workshop, habitually in the cafe over some cake. Rod Bunn from BSRIA joined us this time to check that we were still on track, almost a year after he helped me to introduce the soft landings framework to our UEA project stakeholders. We are in Stage 2 of the framework and we are really getting a grasp of what it’s all about, Stage 2 focuses on design development, reviews similar projects and details how the building will work. Over the last two months we held some ‘reality checking’ workshops on various topics and have gathered some great feedback on our RIBA Stage D design. This will be used to shape the detail as we move into RIBA Stage E design.

During our soft landing gatherings, the champions are challenging ourselves with thoughts like:

  • are the BREEAM Outstanding & PHPP figures really relevant to our building users? How do we demonstrate their great value to the users?
  •  ensure that our soft landings champions are empowered, to ensure that they are accommodated by the wider project team
  • can we recognise and utilise people’s talents and abilities and identify the environment in which they function most effectively?
  • has the soft landings process captured all of the creative ideas from the wider project team? 

We are also looking to create a back-casting report on Post Occupancy Evaluation and occupancy satisfaction by the

Soft landings delivery plan

Soft landings delivery plan

next meeting. We glanced through a few examples of what the client would like to see. Thinking about this report now (that will be needed in say 2 years time), is an example of how the  progressive, forward-thinking approach of soft landings will provide benefit to the client at no additional cost.

Our soft landings meetings are productive, I look forward to these, and it’s not simply about the cake!

Have you included Soft Landings in any of your projects? What are the challenges and achievements you’ve faced?

Getting life cycle costing right

Stuart Thompson

Stuart Thompson,
Senior Design Manager,
Morgan Sindall

A guest post by Stuart Thompson of Morgan Sindall 

The NRP (Norwich Research Park) Enterprise Centre project is an Exemplar Low Carbon Building, which is targeting BREEAM Outstanding and Passivhaus Certification.

The project for the University of East Anglia (UEA) is being delivered using a collaborative single point of delivery system by main contractor Morgan Sindall and its team, which includes architects Architype, civil, structural and environmental engineers BDP and Churchman Landscape Architects.

The centre has been created to achieve a 100-year design life and aspects of the development will be constructed using traditional methods. Locally sourced materials including Thetford timber, Norfolk straw and heather, chalk, lime, hemp and flint will be used and the lecture theatre will be constructed of rammed chalk while various buildings will be thatched. The development is expected to be completed in early 2014.

A key aspect of delivering the Exemplar Low Carbon Building at UEA is ensuring that the project has the lowest life cycle cost possible. The life cycle cost of a project is often discussed in construction but not usually followed through therefore it’s been fantastic to work with a client team which is happy to dedicate time and resources to evaluating this aspect of the development in such detail.

As part of the life cycle costing process, the design team met with consultants from BSRIA to consider how the building’s Passivhaus specification might affect its life cycle output. It was reassuring to know that the early analysis proved that the Passivhaus specification has life cycle benefits. You can watch a film about our workshop below:

 

Following the initial life cycle study, we followed up with a workshop that included a mixed group of various representatives from the client team. We learnt more about which issues were of particular interest to the various client representatives, such as predicted energy costs, climate change considerations, maintenance, robustness of filters and the type of finishes used. The debate did not simply focus on the initial capital costs, but also about legacy issues, robustness and replacement. We covered a full range of topics, including energy source, landscape materials, PV and roofing, lighting and floor finishes. The client maintenance team fed back to the group about their current issues and concerns too.

BSRIA's Peter Tse at the workshop

BSRIA’s Peter Tse at the workshop

What was interesting following such detailed debate was we were able to address the long term issues and this changed our initial concepts within the life cycle analysis. Our changes have made our project report totally specific and the real use and maintenance scenarios follow the life of the building. For example, how often timber windows will be re-painted, how often timber floors will be sanded and sealed and whether the LED light fittings will be able to handle the lamp life and transformer life claims. The workshop allowed the group to ensure that the life cycle analysis is extremely relevant and targeted to this specific project and we will now be able to use the information garnered during the process to shape the scheme over the next few months when detailed design commences.

This landmark project is part-funded by the European Union through the European Regional Development Fund (the largest single ERDF project in the region in the 2007-2015 funding round) in addition to funding from UEA, the Biotechnology and Biological Sciences Research Council (BBSRC) and BRE.

BREEAM – What’s your opinion?

BSRIA recently held an event as part of our Building Environmental Assessment Network to discuss opinions on BREEAM.  This is always a hot topic with lots of views, and this event was no different.

For those new to the world of environmental assessment, BREEAM (the BRE Environmental Assessment Method) is a criteria based assessment of the sustainability of a building.  Developed by the BRE in 1990, it is now the UK’s most used environmental assessment method, and is often a requirement of planning.  More details can be found at www.breeam.org.

The aim of the event was to see if the 2011 changes were sitting well with the industry or needed changing.  It was also a chance to give BRE feedback directly for future changes, or problems that have been encountered.

Particular issues raised were:

  • The transparency of some of the calculation methods
  • Getting feedback or answers to queries from BRE
  • Issues with the energy credits in the 2011 version, especially when dealing with CHP units. 
  • Some refrigeration related credits appear impossible to get

Questions raised in the presentations were:

  • Is the value of each credit appropriate?
  • Is the industry ready for all the changes made in 2011?
  • Is the qualification route for assessors and BREEAM APs appropriate?
  • Is there need for more information for the industry?

The presentations given on the day are available from: http://www.bsria.co.uk/services/membership/networks/building-assessment-network/

So do you have an opinion on BREEAM?  What works well and what needs some adjustment?  Of particular interest would be your experience of the latest version of BREEAM, i.e. 2011.