Taking action on Climate Change

by Michelle Agha-Hossein, BSRIA Building Performance Lead

Most nations now recognise climate change as an established, perturbing fact that needs immediate attention. We can see the effects in the worsening and more frequent extremes of weather: flash floods, droughts, strong winds, heavy snow, heat waves, etc.

UK temperatures in 2019 were 1.1°C above the 1961-1990 long-term average and it was a particularly wet year across parts of central and northern England. Still fresh in the memory are storms Ciara and Dennis in February 2020 with strong winds and heavy rain that caused significant damage to homes and commercial buildings. There is growing evidence that periods of intensely strong winds and heavy rain are likely to increase in the future.

The UK is not the only country affected by climate change. Many other countries are (and will be) suffering disproportionately. The world’s leading climate scientists have warned that we might have just 12 years to keep global warming at a maximum of 1.5°C. After this point, the risk of extreme weather conditions will significantly increase. The increased frequency and intensity of extreme weather will affect all but is most likely to bring catastrophic consequences in many less economically developed countries, where food shortages and water scarcity can trigger deep social changes.

Immediate radical action is required to limit carbon emissions, and the built environment industry can play a crucial role by changing the prevailing culture.

Most building-related carbon emissions are generated from energy use in buildings. However, there are choices that building owners/operators can make and initiatives that they can undertake to lessen the related negative impact on the environment:

In brand new buildings, the most effective way for addressing emissions is reducing consumption through energy efficient design. In existing buildings, the issue can be addressed by efficient retrofitting and effective maintenance strategy. Adopting renewable energy technologies in both cases can significantly reduce building emissions.

Steps building owners and operators can take today.

There are several initiatives/activities that can help building owners/operators combat climate change:

  • Consider ‘net-zero carbon’ targets for your building: UKGBC launched its Advancing Net Zero programme in 2018 and published the ‘Net Zero Carbon Buildings: A Framework Definition’ in 2019. The framework provides the construction industry with clarity on the outcomes required for a net zero carbon building.
  • Ensure the required outcomes for a ‘net-zero carbon’ building are achieved: As advised by UKGBC in the framework definition, initiatives like BSRIA Soft Landings should be adopted in new build as well as in refurbishment projects to ensure a net zero carbon building will be achieved. The BSRIA Soft Landings framework provides a platform for project teams to understand the required outcomes for their project and ensure all decisions made during the project are based on meeting those outcomes.
  • Maintain your net zero carbon building effectively: Business-focused maintenance is a methodology developed by BSRIA that can be adopted to help building operators maintain critical assets effectively and efficiently to sustain a net zero carbon building within budget.
  • Investigate failure quickly: Is the energy bill for your building higher than it should be? Investigate the problem as soon as you can. The first and easiest step would be looking at the energy end use breakdown to see which areas are using more energy than expected. If the issue is related to the HVAC system, check the system’s setting points and monitor the indoor air temperature and relative humidity. Thermal imaging of the fabric of the building can also help to identify, thermal bridging, missing/damaged insulation and areas of excessive air leakage.
  • Promote a healthy diet among building occupants: This is a non-technical initiative that building owners/operators can adopt in their buildings. Eating less meat and gradually shifting to more plant-based foods is vital for keeping us and our planet healthy.  It is important to think about initiatives such as using signage or lunchtime talks, to educate building occupants about healthy diets and encourage them to eat more fruit and vegetables. Research has shown that adhering to health guidelines on meat consumption could cut global food-related emissions by nearly a third by 2050. Healthy diet is also supported by Fitwel and the WELL building standard.

Building owners and operators, to play their role in combating climate change, should ensure their decisions and the way they create and run their buildings contribute positively to the wellbeing of our planet and its citizens.

So, make a start today and choose the first thing you are going to assess/change in your building to help combat climate change.

To find out more about how BSRIA can help you improve building performance, visit us here.

Construction quality could be catching up with other industries

This blog was written by Lynne Ceeney, Technical Director at BSRIA

If you order steak and chips at a restaurant, but the waiter delivers hake in strips, you would be rightly annoyed. Instinctively you blame the waiter, but it could have been a problem with the ordering software, a misreading in the kitchen or just the wrong dish being picked up.  Whatever, you would send it back – it is not what you ordered.   In new buildings, this happens all the time.  Poor communication during the briefing, design and construction process, and poor handover and operation leads to a building that doesn’t deliver the performance the client thought they had ordered in the first place.  Unlike a dinner, it’s not practical to send a building back and wait for the one you asked for to be delivered.  Instead extensive snagging lists, expensive defect resolution and defensive “best we can do” fixes by the facilities team are often used to try and get the building closer to its intended performance – and “closer” is usually the best that can be achieved. The owner and occupier end up with a disappointing building, and the designers and construction company are left with a disappointed client.  The blame chain spreads, and it’s hard to pin down the fault.

The impacts run way beyond disappointment.  Occupier discomfort impacts staff retention, and the increased societal focus on wellbeing indicates that employees will expect higher standards from their place of work.  Poor commissioning or confusing controls mean building systems that don’t work properly and need constant attention or premature replacement, as the uncomfortable working conditions impact on worker productivity.  Inefficient buildings use more energy requiring more cash and causing more carbon emissions.  In fact buildings contribute 37% of UK green house gas emissions from gas heating, and consume 67% of the electricity used in the country.  It’s no wonder that larger investors are taking much more of an interest in the sustainability and performance of buildings rather than just the upfront capital cost.  Good buildings are an asset, poor buildings become an expensive liability in terms of operating costs and void periods. Competitive property markets compound this situation.

With a typical building having a life expectancy of at least 60 years, we are building in problems for this generation and the next.  We’re not great at mass retrofitting, (and the high demand for additional building stock means a capital, skills and material shortage) so we need to get it right first time.  Effective management tools with this aim abound in other sectors, for example DRIFT, (Doing it Right First Time), Six Sigma, LEAN and Zero Defects.  We see the approach being used in food manufacture, car making, pilot training, and patient healthcare, to name but a few sectors.  So what about construction?

Soft Landings is the equivalent tool for the construction sector.  This tried and tested process was developed to help to produce better performing buildings – not necessarily exceptional in performance, but buildings that deliver in operation what they were designed to do in the first place.  Getting a building right requires a shared focus on operational performance of the building right from the start, and throughout the design, construction and commissioning process.  The use of Soft Landings delivers this shared focus, improving communication and collaboration between all parties in the building delivery chain.  It helps everyone to avoid the pitfalls that diminish operational building performance. It fits with RIBA stages, integrates into existing construction processes, and does not require a specific building procurement model.  You can download Soft Landings guidance from the BSRIA website .

However it is always helpful to find out about real world experiences, and to talk to others who are using Soft Landings to help them to produce better buildings.  With this in mind, BSRIA have organised the 2017 Soft Landings Conference (June 16th 2017 at RIBA, Portland Place, London W1B 1AD). You will hear from a range of speakers from different parts of the construction process – including clients – who will explain how they have used Soft Landings in their projects, and the value that it has delivered for their buildings.  You will also hear their hints and tips, and there will be plenty of time to ask questions and take part in discussion both in conference and over lunch.

It’s time for the construction industry to catch up with other industries in terms of quality, to produce buildings that perform as expected, through a delivery process that gets it right first time.  Soft Landings is a process that helps the delivery chain to do this.  For more information on the conference please contact our Events Manager, Tracey Tilbry.

 

Contractors can’t build well without clients that lead

Did anyone see the recent news story on the Edinburgh PFI schools with structural failures? In 2016 we shouldn’t be constructing buildings with feeble brickwork. We have Victorian and Edwardian schools that have been standing for over 100 years without these problems. More ironically we have 1960s CLASP schools – built on a budget with the flimsiest of constructions – still standing and performing their role well after their sell-by date. OK, they’re usually freezing in winter and boiling in summer, with asbestos in places a power drill shouldn’t reach, but at least they’re still standing.

The reasons for these high profile failures are easy to park at the door of the PFI process. One can blame cost-cutting, absence of site inspections, and lack of quality control. Some even say that the ceding of Building Control checks to the design and build contractor is a root cause: site labour can’t be trusted to mark their own exam paper when their primary interest is to finish on time and under budget.

Some commentators blame the design process, and bemoan the loss of days of the Building Schools for the Future programme when design quality was overseen by the Commission for Architecture in the Built Environment (CABE). The erstwhile CABE may have tried to be a force for good, but project lead times become ridiculously long and expensive. And would it have prevented structural failures? Hardly likely.

The one cause of these failures that doesn’t get enough press coverage is the important client leadership and quality championing. It can be argued that clients get what clients are willing to pay for, and there’s no industry like the construction industry for delivering something on the cheap. The cost-cutting, the emphasis on time and cost at the expense of quality control – all this can be pinned on a client base that does not lead, demand, oversee, and articulate what it wants well enough to prevent the desired product being delivered at the wrong level of quality at the wrong price.

Which means that clients have to a) get wiser on what can go wrong, b) get smarter with their project management, and c) articulate what they want in terms of performance outcomes. Truly professional designers recognise this, and are prepared to guide their clients through the shark-infested waters of writing their employers requirements. But once that is done the client’s job is not over. They can’t simply hand the job over to the main contractor and turn their back until the job is complete. They need to be closely involved every step of the way – and keep key parties involved beyond practical completion and into the all-importance aftercare phase.

Soft Landings provides a chassis on which focus on performance outcomes can be built. The chassis provides the client with a driving seat to ensure that standards are maintained, along with a shared construction team responsibility to make sure the building is fit for purpose.  The forthcoming BSRIA conference Soft Landings in London on 23 June is a good opportunity to learn how this can be done. It will focus on workshops where problems can be aired and solutions worked through. It will be led by experts in the field who can suggest practical solutions for real-world projects. Why not book a place for you and a client? For more information visit the BSRIA website. 

Government Soft Landings

This is a blog by Peter Corbett, Principal Quality Inspector at Essex County Council

This is a blog by Peter Corbett, Principal Quality Inspector at Essex County Council

As a Local Authority employee I am well aware of the push for both savings and value for money, it is therefore reassuring to see the importance the Government is affording their version of ‘Soft Landings’.

The Cabinet Office sees soft landings as the ‘golden thread’ of BIM, rather than a delivery tool, and is looking for three key benefits from its implementation, those being; Improved Environmental Performance, Improved Financial Performance and Improved Functionality and Effectiveness.

The Government’s Soft Landings policy drawn up in September 2012 recognised that ‘The ongoing maintenance and operational cost of a building during its lifecycle far outweighs the original capital cost of construction, and GSL identifies the need for this to be recognised through early engagement in the design process.

To help the development of GSL a stewardship group was formed to which all government departments and agencies were invited. This group generally meets quarterly with around twenty department and agencies represented. It seeks to update the GSL implementation progress across departments, develop training ideas and determine ways of measuring the benefits that could be gained from the process.

GSL has been the archetypal snowball, steadily gathering pace as it moves toward 2016 when the Cabinet Office has asked for its adoption by all central government departments and agencies, and gradually increasing in size, as with each stewardship meeting more departments and agencies are in attendance.

I was fortunate enough to receive an invite to the last GSL stewardship meeting through my links with the BSRIA Soft Landings User Group and as a Local Authority representative, and was encouraged to see the enthusiastic approach to soft landings from some of the more engaged departments, they like ourselves see the advantages soft landings could offer (albeit from an FM focussed approach that more considers the ‘In Use’ benefits) and are eager for the evidence of this that case studies and their like could provide. Of course as with most matters concerning Central & indeed Local Government the journey is never straight-forward, and as could probably be expected the speed of soft landings adoption varies greatly both in levels of commitment and of development between each Government department and agency.

So what next for GSL? On Friday 7th November there was a GSL supply chain engagement day, to which all Government departments and agencies were invited and encouraged to extend invites to their design, construction and facilities management partners. Attendees were treated to seminars on what Government Soft Landings actually are, why they should be used and how they should be implemented, as well as what training and ongoing support could be provided.

Soft_Landings_logo-highIt was fairly evident from the nature of the questions from Government department representatives that there remains a lot of work to do to obtain both a participative and consistent approach across all departments, as well as the difficulty in impressing on the supply chain providers that success on a project is not merely about building to budget and programme. As pointed out by one contractors’ representative ‘We know of Soft Landings, but that’s where our knowledge ends’, a better description of what GSL actually is was requested with examples of what ‘success’ actually looks like, and also recognition that there is a clear shift from Capex to Opex in the governments construction expectations. All evidence that there is still much to do to achieve wider engagement in soft landings throughout the industry.

But there remains a high level of commitment to soft landings from the Government as evidenced by this event, and this is likely to soon have an impact on those of us in Local Government. In my own Authority we have been using the principles of soft landings in order to help improve the delivery of our projects in areas that have proved problematic; this has predominantly centred on the handover and defects resolution stages, and also end-user training on their new building. For us the ethos of soft landings has been extremely beneficial, but we have been fortunate enough to get the buy-in from our framework of contractors, again some contractors are more engaged with the practice than others, however with the Governments push for the use of soft landings it should encourage everyone’s participation in the process, and hopefully to the benefit of all involved; commissioner, client and contractor.

 

Blogger profile

My working career began early 1980’s in civil engineering, after taking various qualifications I moved into construction after an acquaintance encouraged me to become a clerk of works at the age of 21.  I joined Essex County Council initially as an assistant clerk of works and have remained with the authority for almost thirty years, latterly as the authorities Principal Quality Inspector. I have more recently acted as the construction performance manager on Essex County Council’s Contractors Framework, for which I am undertaking the role of Soft Landings champion. I am a Fellow of the Institute of Clerks of Works and the Construction Inspectorate having first joined the organisation in the 1990’s.

The “Seven pillars of (BIM) wisdom”

In 2011 the report for the Government Construction Client Group defined Level 2 BIM as being:

“Managed 3D environment held in separate discipline “BIM” tools with attached data….”

However, as a consequence of ongoing development of the processes and tools available, and feedback from early adopter projects and other industry experience, the Government has recently refined its definition of Level 2 BIM as having the following seven components:

  1. PAS 1192-2:2013 is available to download for free from BSI

    PAS 1192-2:2013 is available to download for free from BSI

    PAS 1192-2:2013 Specification for information management for the capital/delivery phase of assets using buildinginformation modelling

  2. PAS 1192-3:2014 Specification for information management for the operational phase of assets using building information modelling
  3. BS 1192-4 Collaborative production of information. Part 4: Fulfilling employers information exchange requirements using COBie – Code of practice (due to be published Summer 2014)
  4. Building Information Model (BIM) Protocol
  5. GSL (Government Soft Landings)
  6. Digital Plan of Work (in preparation)
  7. Classification (in preparation)

 

1. PAS 1192-2:2013 builds on the processes described in BS 1192-2007, and introduces new concepts such as employer’s information requirements (EIR) – the employer’s expression what information they require from the project and the format it should be in, and BIM execution plans (BEP) – the supply chain’s response to the EIR showing how it will meet its requirements.

Read more of this post

Review of the BSRIA Briefing 2013 – Changing Markets, New Opportunities

“Construction is the last of the big industries to go digital”, John Tebbit, Construction Products Association

November 2013 saw another brilliant BSRIA Briefing held as always at the fantastic Brewery in London. The event was chaired by John Tebbit, Industry Affairs Director at the Construction Products Association with c400 industry professionals in attendance. The speakers this year were focusing on customer satisfaction, data centre trends, changes in building practice and design decisions, smart technology leading the industry forward and the internet of things.

Chairman John highlighted two key issues facing the industry, the Construction 2025 strategy and the move towards Low Carbon as well as the construction industry being the last industry to go digital despite a demand to do so.

Bukky Bird talked about Tesco as a continuously changing organisation by highlighting some of the company’s historical milestones. From Tesco’s founder Jack Cohen opening a market stall in 1919 to becoming a global company with just over half a million colleagues today.

Bukky also highlighted some current customer expectations and key drivers for this such as the current economic context. She emphasised the need for organisations to understand and respond to changing needs and environments.

“A green agenda is a prerequisite of what customers expect from a brand like Tesco”, Bukky Bird, Tesco

“A green agenda is a prerequisite of what customers expect from a brand like Tesco”, Bukky Bird, TescoToday’s customer is under pressure, struggling with rising costs and dealing with lifestyle changes. The focus is therefore on family and the home, with a real expectation that brands should reduce waste and save money. Responding quickly to these needs is critical for retailers like Tesco and this should therefore drive the focus through the industry supply chain.

A challenge facing our industry is how to develop true partnerships to tackle these problems. Bukky highlighted the need for flexibility, agility and the need for the industry to be willing to change. The customer is changing radically and the building industry needs to be ahead of this curve.

Historically we have been very slow to adapt, and this is an opportunity to buck that trend. Her final point was that the industry are not supplying Tesco, but Tesco’s customers – understanding the customer’s needs and developing innovative solutions to meet these is key to successful partnerships.

“Nobody ever did anything to be green, they did it to save money”, Nicola Hayes, DatacenterDynamics

 Nicola Hayes looked at a rather different sector focusing on data centre trends and energy. Datacentres Nicola argued are the buildings you do not see, the hidden side of the industry and yet becoming a central part of several industries as people relocate their data to the Cloud. Nicola discussed the fact that Datacentres may be hidden but they do suffer negative publicity mostly due to the energy usage of such buildings and the accusation from the Press that they are singlehandedly destroying the planet. When viewing the industry as a country, the industry uses a little less energy than the UK as a whole, marked at 332.9TWh which is an exceptional amount and understandably a worry for the industry and a target from the Press.

But it was the trends that Nicola was concentrating on, where the Datacentre industry has come from and the expectations of it for the future. In three years the industry has grown from $86bn to a staggering $120bn as well a doubling in space used for the buildings, growing from 15million sqm to 31million sqm. The growth of Datacentres is down to several other key industries, the rate of increase has risen for Professional Services, Energy & Utilities, Industrial & Process and Media & Telecoms. With this growth there has been a change in how Datacentres are being built and their operations. There has been a 15% increase in outsourcing for the industry since 2007 rising to nearly a quarter of the industry but IT Optimisation still remains a major investment.

For the built environment the biggest change Datacentres has had for them is the increase in energy monitoring and the storage of millions of data bits. People in the world, particularly the US, UK and Germany are starting to become more conscious of energy efficiency therefore more business is generated for the Datacentre industry through big data from energy monitoring. Nicola pointed out that this is not done for a purely ‘green’ reason but primarily to monitor costs which are why most universities do not monitoring as they are not responsible for the financial side of their energy use.

With there being such a focus on energy efficiency, the way Datacentres are being built has also been a changing trend with there being 25% increase in the number of retrofits of Datacentres while there was only a 2.1% increase in the number of new builds. Efficiency measures (to answer to the Press criticism) are also now determined from the outset. However despite Datacentre industry growing at a fast rate there are risks involved for the industry from the small scale of compliance to the large scale of terrorist attacks. With these risks comes an important debate that is happening within the industry, cost vs. risk.

“There is a market for MVHR but we need to get better at delivering it”, Nigel Ingram, Jospeh Rowntree Housing Trust

 Nigel Ingram continued with a discussion about social housing and the consideration of end users when designing buildings. The Joseph Rowntree Housing Trust currently looks after 2,500 homes in Yorkshire and Hartlepool. Nigel discussed one particular project the Housing Trust are involved in, the Derwenthorpe village which looks at the lessons learnt from past projects and how they can improve their buildings. The way the Joseph Rowntree Housing Trust decided on best building practices was through experimentation over four years, they built two prototypes and used 17 different methods and as many M&E components as possible including grey water harvesting and block work systems. The aim of this experimentation was to see what worked to create the best possible building.

As well as all these design considerations Nigel also enforced the importance of the end user and their lifestyles with the Joseph Rowntree Housing Trust looking at how people live in buildings and what changes in lifestyles are expected in the future and how best can the prepare buildings for that. There were three main points that made up the JRH’s strategic servicing infrastructure, the first being fibre optics. The Trust believes that with the use of technology ever increasing including internet, television packages etc. they needed to invest in a viable cabling network. However none of the big companies were prepared to discuss such a project therefore the Trust developed a joint venture with an investor to set up their own fibre optics for the estate, by doing so they satisfied the customers and set them up for any increase in connectivity in the future.

The second point the Trust considered was Communal Heating, they looked at a variety of different heating techniques for the estate such as low ground source heat pumps.  Communal Heating was decided on in 2007 from a carbon footprint point of view as at the time the Code of Sustainable Homes was announced with zero carbon targets by 2016. Communal Heating is notoriously difficult to get working efficiently, just like any heating system however after it was distilled down into the six components that worked for the Trust it was able to provide fuel security and prince control for the future residents which is what users wanted from their buildings. The system now works and is one of the only systems in the country that is successful and has been contracted for 25 yrs to a European Communal Heating group.

However Nigel wanted to point out that the Derwenthorpe village has not been completely successful, the final point in their strategic servicing infrastructure was MVHR Systems. The project has not seen any success with these systems, it has been installed in 64 houses but customer feedback has been negative and there are many issues with it. As an alternative MEV is now being used. Nigel stresses that there is a market for MVHR systems but for it to work there needs to be massive improvements in the industry in terms of commissioning, installation and maintenance. There seems to be a technology focus rather than process and this needs to change if the industry is to satisfy clients and users of buildings.

Nigel’s main focus for the Derwenthorpe project was customer satisfaction, the importance of the end user. Fibre Optics and Communal Heating was installed for the benefit of the residents of that estate as they have certain expectations of the way they live including operational and financial. The Joseph Rowntree Housing Trust has focused on the end user for their design plans rather than what should work from the industry perspective. Rigorous testing and accepting systems aren’t right has gone into making sure buildings are built as best as they can be which is important for our industry, it’s taking into consideration the mistakes made on previous building stock and learning from them and also considering the occupants and their needs.

“The Cloud is as suited to small buildings as it is to big buildings or building portfolios”, Jeremy Towler, BSRIA

 Jeremy Towler reflected on the “smart” built environment and how we get there. Jeremy highlighted that there is a lot happening and changing in our industry emphasising that we are the last industry to go digital despite there being several opportunities for digital work particularly wirelessly. BEMS will become an increasing component of buildings, modules will be built off site and therefore digital technology needs to be an important investment. Mobility will also become a more important part of the built environment, currently everyone uses a mobile but with geo-location buildings will be able to recognise everyone in buildings and respond dynamically. With this the collective voice of the occupants starts to influence the building which could be quite revolutionary.

Building Analytics are also an important step towards a “smart” built environment, increasingly buildings have sophisticated software that permits building operation and how best to optimise them. With Building Analytics becoming a more common part of our industry there has been a move towards the Cloud which has allowed data mining to reveal relationships and trends we never could have imagined. With these advances also comes the development of Smart Cities, particularly in China where there is a commitment to build at least 30. Jeremy defines smart cities as an incorporation of intelligent buildings, broadband connectivity, innovation, digital inclusion and a knowledge workforce.

But Jeremy states it’s not just smart cities we have to consider, its smart grids and smart buildings. Smart grids is an advanced power grid for the 21st century, essentially it is a decentralised multi directional model where energy and information can flow from supplier to consumer and vice versa which enables a variety of new applications for homes and businesses. Smart homes on the other hand have reached a critical mass and are due to break into the standard housing market but with this there has been an opportunity seized by the utilities who are now offering connectivity.

With smart homes becomes the internet of things and the ‘ubiquitous homes’ where sophisticated systems learn behaviour and respond accordingly, like our mobile phones that can tell us where we want to go and how we need to get there, such software will be used in our own buildings to provide our homes with the settings that we need. However the current built environment is a long way from becoming a smart industry, currently more than 75% of the building stock has no intelligent controls which is primarily to do with the age of the buildings with over 40% of total stock being built before 1960. With this in mind there is an opportunity for the industry to consider a great deal of retrofit projects but for smart technology to work to its best potential for the built environment the industry needs new skills developed through training in software and hardware analysis.

“We are now accountable for how our buildings perform “, Michael Beaven, Arup Associates

 Michael Beaven continued on this theme of the industry needing to change but instead focused on workflows. Arup has learnt that change is beneficial to the industry, adaption is necessary to meet the needs of the client. Arup have changed what they do and how they do it, learning that doing things the same way over and over again is to no benefit. However despite the need to adapt there are constants within the industry, carbon being the main issue for energy costs and emissions for companies in reputational aspects as well as the bottom line an example being Sky who are very forward looking including reducing the carbon of their set top boxes from 10 to 4 watts saving 20megawatts to the grid.

Importance of energy and efficiency is paramount but so is what we build it with. Embodied carbon is a key player in how we build our buildings now; decisions are being made on where products come from and their whole life cycle rather than primarily cost efficiency. Buildings are also being tested now, everything is monitored in our buildings so we can learn how to improve them, we are accountable for how buildings perform. From this we can learn how to design buildings that are successful for end users.

Michael also emphasised Jeremy’s point of the internet of things, how the integration of IP controls are making building betters and even the advancement of BMW considering smart transport for smart cities. Building on the interaction between traffic signals and mobile data to develop relationships between them to better control traffic, even where you park will be managed in a smart way. Another important development in terms of smart technology is that people are now connecting and sharing information on what works for a building and how best practices can be established.

One of Michael’s most important arguments was the importance of BIM and the matter that we as an industry really need to get up to speed with it. It’s client driven so we need to be on board as it is not only changing our workflows but also our business, without a grasp we lose projects. There also needs to be an acceptance that BIM is not just about 3D drawings and design but rather it should be a changing of our work streams to digital.

BSRIA Briefing panel answers questions from the audience

Michael’s final point tied in one of the key themes of the morning, customer satisfaction or rather the importance of the end user. Arup are moving towards an end user focus, designing buildings for people rather than the client or the architect. He used Sky as an example of a company championing a place for people, designing a building that understands what the user wants rather than what is considered the best design. Michael emphasised the feedback loop, empowering people to vocalise what they want in a building, what controls work for them, with that Soft Landings is critical for discovering what works and what doesn’t and resolving these issues before a project is completed.

There were a variety of thoughtful questions throughout the morning ranging from what the industry is doing to combat the UK’s power supply reducing to 2% by 2016, John Tebbit argued that the UK needs to stop investing in the UK and instead build industry abroad and import into the UK. There was also discussion on why there are so many installations problems within the industry, Nigel Ingram suggested there was too much blame placed on the end user, that there needs to be more ownership of mistakes and to learn from them if the industry is to move forward. This was the key theme throughout the morning, for the industry to move forward in any pursuit especially digitally we need to focus on trends and accept change as a good thing. But when accepting change we also need to learn from our past mistakes rather than continue to avoid them.

“Change comes from doing 100 things 1% better”, Sir Clive Woodward

Following lunch guests were treated to an afternoon speech from Sir Clive Woodward who continued the theme of change being necessary to move forward and how that worked for the England rugby team and the British Olympic team. Sir Clive’s talk looked at the 3F’s or 6F’s argument and interestingly the importance of an Australian dentist and his impact on working habits. He emphasised the effort of a whole team being behind any win and argued that talent is not enough but learning, calmness and hard work are needed to leverage it.

A special mention also goes to Chris Monson, of main sponsor Trend, who was awarded an Honorary Membership of BSRIA, becoming only the 8th person honoured. Chris accepted the award from BSRIA Chairman Leslie Smith and thanked the company as well as the industry.

A big thank you to all delegates that attended and the speakers who gave their time to the event. Also thanks to Sir Clive Woodward for being our afternoon speaker and rounding up a fantastic Briefing.

To download the presentations from the event go to BSRIA’s website.

How to procure Soft Landings

BG 45/2013 Soft Landings procurement Guide

BG 45/2013 Soft Landings procurement Guide

BSRIA has just launched its latest guidance on the Soft Landings graduated handover process.   How to Procure Soft Landings – guidance for clients, consultants and contractors is designed to help clients and their professional and building teams frame their Soft Landings requirements in a consistent and structured manner.

 The guide is a response to two clear trends in the use of Soft Landings. Primarily, clients aren’t sure what they are asking for when they call for it in tenders. Construction firms are seeing wide differences in client requirements. The initiated clients may spell it out, but for every expert client there are 20 who simply ask for Soft Landings without a clear idea of what it is.

 Many builders and contractors, particularly those not up with current thinking, are similarly clueless on how best to respond. That’s one of the downsides with an open-source protocol – the viral spread of Soft Landings is a good thing, but a lack of certification and control means that the uninitiated can easily catch a cold.

 Second, Soft Landings is being adopted by central government as a formal procurement policy. This is Government Soft Landings (otherwise known as GSL), a Cabinet Office-inspired interpretation of Soft Landings for government clients. While it’s not a million miles away from the official version published by BSRIA and the Usable Buildings Trust, GSL takes a more facilities management perspective of the process and focusses far more on getting guaranteed outcomes from the construction industry. GSL is slated to be mandated for central government projects in 2016, along with the adoption of Building Information Modelling (BIM), with which Soft Landings is well-suited.

 So what we have, then, are commercial clients still a little confused in their (voluntary) adoption of Soft Landings. On top of that is an incoming group of government clients, building anything from schools to prisons to aircraft hangers,  for whom Soft Landings is a huge unknown but who will be mandated to adopt it. BSRIA’s view is that it might be a good idea to lay out the best ways of expressing Soft Landings in client requirements, pre-qualification questionnaires, and invitations to tender, so that the clients and industry alike get greater consistency in Soft Landings projects from the very outset.  

 The procurement guide has benefited substantially from the Soft Landings User Group, a BSRIA-run team of clients, architects, consultants and contractors who have learnt from experience on Soft Landings projects what works well and what doesn’t. This learning has been used to create practical, generic requirements for Soft Landings activities that can be used in project documentation. 

 A body like the User Group is absolutely vital for the practical development of Soft Landings. BSRIA knows it doesn’t have all the answers, and in any case should not dictate how Soft Landings is put into operation on real projects. Each project has its own needs and objectives, and each form of procurement throws up its own set of opportunities and challenges. The trick is to find out what works in each context, and try and find ways round thorny issues like novation and cost-cutting for instance, both of which can compromise the best of intentions.

 The guide provides specifically-worded requirements for each step in each of the five stages of Soft Landings.  The guidance is split into three sections, with requirements worded for clients appointing professional designers, clients appointing main contractors/builders, and contractors appointing sub-contractors.  Inevitably, there is some repetition, but the guide gets round that at relevant points by referring the reader to sections in the guide where a specific requirement is more logically located. 

Stage 3 - Pre-handover

Stage 3 – Pre-handover

The example shown is typical. Energy metering installations are proving to be a major problem – they are installed to satisfy Building Regulations, but are often not set up in a way that makes them useful. Although the Soft Landings Framework calls for an energy metering strategy, the procurement guide goes a step further by spelling out what should be provided, in this case at the pre-handover stage. Each requirement is supported by explanatory text that gives the main contractor, in this instance, some background context and the reasons for the requirement.

 Some Soft Landings stages may have more than one worded requirement. Some optional requirements have also been provided, for instance in the aftercare stages where it may be important to spell out precisely who should be involved and for how long.

 For example, under the core requirements for main contractors appointing sub-contractors, contractors have the option of requiring a subcontractor to be retained to assist the client and other members of the project team during handover, and afterwards to monitor the building’s performance. Some sub-contractors may be required to be based on site full-time during the initial aftercare period to assist with end-user queries and to undertake fine-tuning of systems. This would not typically apply to a ductwork sub-contractor, but it would usually apply to a controls sub-contractor. More critically, it could apply to any contractor whose systems or components come with automatic controls, particularly those with bespoke communication protocols (seemly most of them) which can only be adjusted by the supplier after payment of a fat call-out fee. If you’re nodding at this point, you know how it is. The Soft Landings procurement guide now covers this issue, and many others like it.

 An opportunity has been taken to fill gaps in the Soft Landings Framework, published back in 2009 when practical experience was a bit thin on the ground. For example, the guide contains a generic design work stage which was not included in the Framework. The procurement guide also provides more detailed advice on principles of procurement and tendering, how to include Soft Landings in tender processes and interviews, and some advice on the best way to budget for Soft Landings.

 The timing of the guidance also coincided fortuitously with the publication of the 2013 RIBA Plan of Work, which gave BSRIA the opportunity to align Soft Landings stages against the new RIBA stages, and those published by the CIC. There’s also a public sector Soft Landings decision tree included to help government and local authority clients dovetail their procurement requirements with Soft Landings requirements.

 Building performance research is identifying many critical aspects of procurement where clients and the construction industry need to tighten up their respective acts. The commissioning manager is a critical role, and the earlier they can be appointed the better. The procurement guide offers some advice on how to do this, and what their role should be in Soft Landings.

 Soft Landings is not job in itself but a set of roles and responsibilities shared among the client and project team. However, on large jobs particularly a co-ordinator may be needed to make sure the administration is carried out. Paperwork – which could include updating operational risk registers in BIM models for example – needs to be done by someone. If this isn’t covered, Soft Landings might fail ‘for want of a nail’.

 BSRIA hopes that How to Procure Soft Landings – guidance for clients, consultants and contractors will provide all that clients and project teams need to put Soft Landings into operation.  It is a practical guide to accompany the Soft Landings Framework – still the industry bible on what Soft Landings is about, and why you should adopt it.

 With all this talk about the performance gap between design and building operation, we mustn’t lose sight of the fact that the act of procuring a building and constructing it is a team enterprise. No-one goes into the process with the intention of doing a bad job.  Events, like many things in life, can conspire against it. What Soft Landings tries to do is provide toeholds for everyone involved to do a better job in the face of budgetary, time and skills pressures.  How to Procure Soft Landings – guidance for clients, consultants and contractors provides a whole load more toeholds for everyone.

 BSRIA BG45/2013 How to Procure Soft Landings – guidance for clients, consultants and contractors is available from BSRIA bookshop.

Soft Landings – it’s not all about the cake!

A guest post by Stuart Thompson of Morgan Sindall

Soft Landings Workshop

Soft Landings Workshop

Following on from my previous post regarding the UEA low carbon project I’d like to share our progress with the inclusion of Soft Landings.

Last week our soft landings champions met for our fifth workshop, habitually in the cafe over some cake. Rod Bunn from BSRIA joined us this time to check that we were still on track, almost a year after he helped me to introduce the soft landings framework to our UEA project stakeholders. We are in Stage 2 of the framework and we are really getting a grasp of what it’s all about, Stage 2 focuses on design development, reviews similar projects and details how the building will work. Over the last two months we held some ‘reality checking’ workshops on various topics and have gathered some great feedback on our RIBA Stage D design. This will be used to shape the detail as we move into RIBA Stage E design.

During our soft landing gatherings, the champions are challenging ourselves with thoughts like:

  • are the BREEAM Outstanding & PHPP figures really relevant to our building users? How do we demonstrate their great value to the users?
  •  ensure that our soft landings champions are empowered, to ensure that they are accommodated by the wider project team
  • can we recognise and utilise people’s talents and abilities and identify the environment in which they function most effectively?
  • has the soft landings process captured all of the creative ideas from the wider project team? 

We are also looking to create a back-casting report on Post Occupancy Evaluation and occupancy satisfaction by the

Soft landings delivery plan

Soft landings delivery plan

next meeting. We glanced through a few examples of what the client would like to see. Thinking about this report now (that will be needed in say 2 years time), is an example of how the  progressive, forward-thinking approach of soft landings will provide benefit to the client at no additional cost.

Our soft landings meetings are productive, I look forward to these, and it’s not simply about the cake!

Have you included Soft Landings in any of your projects? What are the challenges and achievements you’ve faced?

How will you invest in Soft Landings?

Budgeting for better building handover

Soft Landings is an open source process designed to overcome problems after handover. It is arguably an increasingly important part of procurement philosophy. Three year periods of aftercare are regularly being considered a core element of project plans; however, with Soft Landings comes great responsibility. The question is whose responsibility is it to include Soft Landings and ensure it gets done?

All clients want high performing buildings but are not always willing to pay additional costs for the aftercare process. On the other hand the building industry has a right to demand additional fees if they are taking on more responsibilities and higher risks. This standoff won’t resolve itself without some easing of tensions.

As an advocate of better building handover, I believe that both clients and contractors need to change their expectations. More fundamentally, both sides of the contractual fence need to recognise that although they may share an ambition for a high-performing building, it does not become such until it is proved to be. This means troubleshooting the building and fine-tuning it way beyond resolving snags and defects.

Once a client acknowledges that it wants its project to adopt Soft Landings, it needs to ensure that the methodology is expressed throughout the entire process. The client should not assume that the contractor will take responsibility for it all; BSRIA has seen a number of documents that puts the responsibility of Soft Landings completely with the contractors when it should definitely be a result of negotiations between all parties involved. A client also needs to be specific in what they expect from their consultants and sub-contractors. Therefore such a project should unquestionably be a collaborative effort with equal responsibility and realistic expectations shared by all.

However, this commitment can’t come for free, which begs a question of where the costs lie, and what they amount to.

Setting aside a budget

It is essential that clients acknowledge that a budget needs to be set aside for Soft Landings, especially if they want a three year period of aftercare. A reasonable place to start is by feeling a nominal budget and then to discuss how it can be best invested, all projects are different but BSRIA believes that 0.1% of the total contract value is a good place to start. Then comes the hardest part, how do you distribute such a budget?

The budget needs to include the three year aftercare period but also other additional Soft Landings activities required during the design and construction process, such as periodic reality-checking. It is also important for clients to note that they will have additional costs at later points if they take into consideration the need for independent building performance monitoring. So, overall, does the 0.1 per cent rule hold true? By and large it’s a good place to start.

If the budget proves inadequate for the client’s ambitions, then those ambitions either need to be scaled back, or the budget increased. Undoubtedly, all parties to the aftercare process stand to gain from the lessons learned, so it is absolutely in their professional interest to meet each other halfway. 

If an agreement and a clear plan can be put into place early then it is entirely possible for such a project to be successful.

To gain a better understanding Soft Landings procurement and budgets read the full article here:

 http://www.bsria.co.uk/news/soft-landings-budgets/